Question/Dilemma about High Bridge Construction...?
    NW Mailing List 
    nw-mailing-list at nwhs.org
       
    Wed May  7 10:43:00 EDT 2014
    
    
  
 
 
 
Bob:
There's one other fact that may confirm that the main
track was shifted from the center of High Bridge.
A quarter mile (or so) west of the Farmville-end of the
bridge, there was an 0.28 degree curve to the left
followed by an 0.28 degree curve to the right.  Curve
had a 1" superelevation.  The M/W Engineering Dept.
called it a "correction".  Possibly this "correction"
placed the main track back to its original alignment.
                                       Harry Bundy 
 